The timeline view lets you represent data in a chronological order.

Timeline views need two configuration fields:

dateStartField (string, required)

The field key that should be used to get the start of the timeline activity.

dateEndField (string, optional)

Same as the dateStartField but for the end of the activity. If left blank, the activity will be considered a one-day event and be displayed as such.

For example, a section config like this:

sections:
  section:
    - name: customer-map
      group: CRM
      type: timeline
      dateStartField: Begin
      dateEndField: End

Would expect each entry to have a Begin and End field with the begin/end dates.

Example data for this section config:

{
  "lastUpdated": 1658756953,
  "sourceIdentifier": "tasks",
  "data": {
    "Begin": "2022-04-07",
    "Title": "Activate SSL-Certificates",
    "End": null
  },
  "name": "Activate SSL-Certificates",
  "key": "POR-4"
},
{
  "data": {
    "Begin": "2022-03-30",
    "Title": "Assign Roles",
    "End": "2022-04-04"
  },
  "name": "Assign Roles",
  "key": "POR-1"
},

Dates need to be supplied in the ISO 8601 format, YYYY-MM-DD. For example: 2022-04-07